How We Work
The GS process, step by step
Every GS Construction remodel follows the same owner-led process: a free in-home estimate, an itemized written scope, permits handled by us, an owner-supervised build you can track in a live client portal, and a final walkthrough backed by a written warranty. Most kitchen remodels take 6–10 weeks and most bathrooms 3–5 weeks, with a written schedule before work begins.
-
1
Free in-home estimate
Week 0Greg or Patryk — the owners, not a salesperson — walk your space, talk through what you want, and take real measurements. You get honest feedback on what your budget buys, grounded in the project ranges we publish openly.
-
2
Itemized scope & contract
Within days of the visitYour proposal is an itemized scope — labor, materials, demolition, disposal, line by line — not a single mystery number. Payment terms and warranty coverage are spelled out in the written contract. No surprise charges on the final invoice.
-
3
Design & selections, your way
Parallel with permitsBring your own designer or architect, use our design-build help, or be your own designer — we send you to trusted showrooms and install what you choose. Selections are scheduled ahead of the build so lead times never stall the site.
-
4
Permits & scheduling
Typically 1–2 weeks in most suburbsWe pull and manage building, plumbing, and electrical permits with your village — Arlington Heights, Palatine, Winnetka, Schaumburg, and every town we serve — and hand you a written schedule before demo day.
-
5
The build, owner-supervised daily
Kitchens 6–10 wks · Baths 3–5 wksOur long-standing trade partners work in sequence under daily owner supervision. Your private client portal shows the schedule (past and upcoming), current change orders, and up-to-date balances — and you always have a direct line to the owners.
-
6
Walkthrough, punch list & warranty
Final weekWe walk the finished project together, close out every punch-list item, hand over manufacturer paperwork, and your 1-year workmanship warranty starts — with the owners a phone call away if anything ever needs attention.
Typical timelines at a glance
| Project | Construction time | Notes |
|---|---|---|
| Kitchen remodel | 6–10 weeks | Custom-cabinet projects can run 12+ weeks due to lead times |
| Bathroom remodel | 3–5 weeks | Large primary baths with custom tile and glass: 6–8 weeks |
| Permits (most suburbs) | +1–2 weeks | Pulled and managed by GS before construction starts |
Every project gets a written schedule before work begins — these are the honest ranges we see across our completed projects, not best-case marketing numbers.
Process questions
- How long does a kitchen remodel take?
-
Most kitchen remodels take 6–10 weeks from demo to final walkthrough. Custom-cabinet projects can take 12+ weeks due to lead times. GS Construction provides a written schedule before work begins.
- How long does a bathroom remodel take?
-
A typical bathroom remodel takes 3–5 weeks. Larger primary bathrooms with custom tile and glass enclosures can take 6–8 weeks. Permits in some Chicago suburbs add 1–2 weeks.
- Who is my point of contact during the project?
-
The owners — Greg and Patryk Szady — from the first call to the final walkthrough, plus a private client portal that tracks your schedule, change orders, and balances in real time.
- Do you handle permits?
-
Yes. We pull and manage building, plumbing, and electrical permits with the village or city for every project that requires them.
Ready to start step one?
Book your free in-home estimate — you'll have an itemized scope and a real timeline before you commit to anything.